A Contractor submits a fully detailed claim for unforeseen ground conditions. Weeks pass. The Engineer holds a couple of meetings, says the claim is “under review”, and then goes quiet. The Contractor assumes the matter can wait until the next progress meeting. The Employer assumes that silence means the claim has gone away.
Under the 2017 FIDIC Red and Yellow Books, silence has a defined meaning. Sub-Clause 3.7 [Agreement or Determination] puts the Engineer on a clock, and it starts a second clock for whichever Party receives the result. Miss the second one and the Engineer’s decision can become final and binding.
What Sub-Clause 3.7 does
In the 1999 books the Engineer’s role in a claim was covered by two short paragraphs in Sub-Clause 3.5. The 2017 editions replaced them with more than two pages of detailed procedure, and the same procedure now applies to claims by either the Contractor or the Employer.
Three features matter before you look at the time limits:
- Neutrality. The Engineer must act neutrally when exercising its Sub-Clause 3.7 duties. The 2017 books do not define the word, and the FIDIC guidance, as summarised by Howard Kennedy, reads it as treating both Parties even-handedly.
- No Employer consent. The Engineer does not need the Employer’s approval before exercising its Sub-Clause 3.7 authority (Sub-Clause 3.2).
- No delegation. The Engineer cannot delegate Sub-Clause 3.7 authority to its assistants (Sub-Clause 3.4).
The clocks at a glance
| Step | Period | Where |
|---|---|---|
| Agreement stage | Up to 42 days | Sub-Clause 3.7.3 |
| Determination stage | A further 42 days (84 in total) | Sub-Clause 3.7.3 |
| Notice of Dissatisfaction | 28 days from receipt of the determination | Sub-Clause 3.7.5 |
| Referral to the DAAB | 42 days after the Notice of Dissatisfaction | Sub-Clause 21.4 |
Stage one: agreement, then determination
The Engineer must first consult the Parties, jointly and/or separately, and encourage them to agree. Only if that fails does the Engineer make a fair determination, taking due regard of all relevant circumstances. The two stages together can take up to 84 days, almost three months. The Engineer may propose different time limits, but they apply only if the Parties accept them.
Where a determination requires one Party to pay the other, Sub-Clause 3.7.4 routes the money through the next Statement and the next Payment Certificate rather than a separate demand.
When the Engineer says nothing
If the time limits pass without a determination, the books supply the answer. A Claim is treated as rejected. Any other matter is treated as a Dispute that either Party can refer to the DAAB without first giving a Notice of Dissatisfaction, as the Clyde & Co quick reference guide and Howard Kennedy both record. Silence is therefore not a pause. For a Contractor’s claim, it is a refusal that arrives on a timetable.
The 28-day trap
A determination is final and binding unless a dissatisfied Party gives a Notice of Dissatisfaction within 28 days of receiving it (or a corrected version). The notice has to carry the title “Notice of Dissatisfaction with the Engineer’s Determination”, state the reasons, and go to the other Party with a copy to the Engineer. It can be limited to part of the determination.
Two points catch people out. First, under the 1999 books a Notice of Dissatisfaction was needed only against a DAB decision, so teams carry over a habit that no longer fits. Second, the notice does not end the matter. According to Howard Kennedy and Clyde & Co, the dispute must then be referred to the DAAB within 42 days, or the notice lapses and the determination becomes final and binding. I could not confirm that second period in every commentary, so check it against the clause text.
An illustration: a determination is received on day 0. The Notice of Dissatisfaction must be given by day 28. If it goes out on day 28, the DAAB referral must follow by day 70. There is no slack for a holiday, an absent signatory or an unclear receipt date.
What contractors should do
- Diarise the 84 days on the day the Claim is received, and confirm in the contract what starts each period.
- Use the agreement stage. Provide particulars promptly, attend the consultations and keep a written record of what was said and offered.
- Diarise 28 days the day a determination arrives. Log the receipt date and who received it. If any part is unacceptable, serve the notice for that part.
- Prepare the DAAB referral in parallel. Do not wait for the 28 days to expire before drafting.
- Treat silence past the limit as a decision. Take advice on the next step rather than waiting for a reply that may not come.
What Employers and Engineers should do
- Engineers: run the process yourself, keep a clock register for every open claim, and write the determination with reasons that show both Parties’ positions were considered.
- Employers: do not make your Engineer wait for instructions on a 3.7 matter. The contract does not require your consent, and a late determination hands the Contractor a deemed rejection and a route to the DAAB.
- Both: read Part B before relying on any of the periods above. Particular Conditions can amend Clause 3 and Clause 21, so the periods on your project may differ.
How to measure it
- Share of claims determined within the 84 days, and median days to determination.
- Share of claims settled at the agreement stage.
- Number of determinations that became final because no notice was given, and whether that was a decision or an oversight.
The bottom line
Sub-Clause 3.7 turns the Engineer’s handling of a claim into a sequence of dated events. Most of the cost of getting it wrong sits in the 28 days after a determination, and those days are easy to lose on a busy site. Put both clocks in the claims register on the first day, and treat every determination as live until the notice period has run. The wider dispute ladder is covered in Dispute Settlement on Infrastructure Projects: The FIDIC 2017 Ladder and Its Time Bars.
If you need help setting up a claims clock register, or an independent view on a determination you have received or are about to issue, get in touch with Amirmehdi ASGHARI at amirmehdi@amasghari.com.
This article is general information, not legal advice. Clause references are to the 2017 FIDIC Red and Yellow Books General Conditions as described in the sources below; the effect of Sub-Clause 3.7 on your project depends on the Particular Conditions and the governing law. Check your contract and take specific advice before acting.
Sources
- Howard Kennedy, FIDIC 2017 Books: Clause 3, The Engineer
- In Principle, Engineer’s determinations under the new 2017 FIDIC standard contracts
- Clyde & Co, FIDIC Quick Reference Guide: Yellow Book 2017
- Fenwick Elliott, Notify now or forever hold your peace: Notices of Dissatisfaction under FIDIC and NEC
- Fenwick Elliott, The 2017 FIDIC dispute resolution procedure: the new dispute resolution mechanism (2018)